Beaumont – Info-Work No 12 – November 1, 2019

Work to come in the next months

The exterior cladding will be completed in mid-November. The landscaping will be underway in the next few weeks on the roof garden and then around the perimeter of the project.

 

Over the past few days, the City of Montreal has completed work on the intersection with the programming of the new traffic light. The intersection is now safe for occupants and future customers of the IGA for entry into the underground parking. IGA will begin work on their premises in November and this will continue until spring 2020.

 

During the fall, it should be noted that the contractor will continue to use a portion of the public domain (street and sidewalk) on the north side of Côte-Saint-Luc Road, between Avenue Earnscliffe and Avenue Clanranald for the different deliveries.

 

We remind you to always pay attention to the restriction signs around the site and using detour paths designed for your safety.

View of the work progress in October 2019

 

Schedule of work reminder

Most of the work will be done from Monday to Friday, between 7am and 7pm. Work could exceptionally continue until 11pm during special operations requiring continuous work without the possibility of interruption. It should be noted that municipal regulations allow work to be carried out every day from 7am to 11pm. If the work is expected to continue during evenings or weekends, the neighborhood will be informed as far in advance as possible.

We remind you that you can reach us at any time by phone, at 514-559-7021, or by email, at info.lebeaumont@hkstrategies.ca, in the case of an event related to the work or to an incident.

Communication with the neighborhood

If you are not already on our mailing list and would like to receive this information and updates on the project, please email us at info.lebeaumont@hkstrategies.ca stating that you would like information on our project by email.

 

The Beaumont team.