INFO-WORK SEPTEMBER UPDATE: The Beaumont project is under construction!

Update: September 7, 2017

Throughout the construction period of the Beaumont project, information on its progress will be uploaded to this page. Updates will be made regularly to keep you informed on the progress of the worksite, as well as the future steps. The project is expected to be completed in spring 2019.

Work to be completed in september and october

The site’s preparation work is now complete and it is currently in the pile installation phase, which will be completed over the next few weeks. Meanwhile, excavation work continues and is on schedule.

Work schedule

Regarding the construction schedule, most of the work will be done Monday through Friday, between 7 a.m. and 7 p.m. Exceptionally, work that requires a continuous effort may go on until 11 p.m. Please note that the municipal regulations allow work to be carried out every day from 7 a.m. to 11 p.m.

A memo indicating the work schedule will be installed at the site over the next few days to remind workers that they must comply with the municipal regulations.

Mitigation measures

As mentioned previously, a construction site of this size can’t be completed without somewhat upsetting the tranquility of the neighborhood. We are therefore taking the necessary measures to minimize the impact of this work on the neighborhood, including:

  • Noise, vibration, as well as trucks and construction equipment traffic: work that can cause noise and vibrations are generally carried out between 7 a.m. and 7 p.m., Monday through Friday. However, if the work needs to be continued throughout the evening, the neighborhood will be informed in advance.
    Please note that a detailed inspection of the foundations and structures of neighboring buildings was completed in the fall of 2016. This inspection has also been recently updated to ensure that vibrations do not affect surrounding homes. Seismographs have been installed in the neighborhood to measure the vibrations in real time.
  • Dust: to limit the dust from spreading, the site and the surrounding streets will be watered when necessary.

Communication with the neighborood

If you are not already on our mailing list, please subscribe to automatically receive work status updates and information. To subscribe, email us at: info.lebeaumont@hkstrategies.ca by stating that you would like to receive information about our project by email.

Do you have a question about the project or have you witnessed an incident on the worksite?

If so, contact us by email at info.lebeaumont@hkstrategies.ca or by phone at 514-559-7021.