NOCA – Phase 1 delivery !

Dear Owners and Future Residents,
We are pleased to confirm that the countdown to the delivery of your new home is well underway. In fact, as we had predicted last May, the first residents should begin moving into their new condo as early as February 2020.
Occupancy should take place in the following order:
Ground and second floors: beginning February 12, 2020
Third and fourth floors: beginning March 4, 2020
Fifth and sixth floors: beginning March 25, 2020
Seventh and eighth floors: beginning April 22, 2020
Please note that due to the winter weather and the on-going construction of phase 2, some of the outdoor landscaping work (terrace, yard work, rooftop swimming pool, etc.) will be unfinished by the time the delivery date rolls around. The work will be completed as soon as conditions permit.
Caution
Please remember to constantly pay attention to the signage placed throughout the work site during construction and to comply with the detours designed to ensure your safety.
Once again, we thank you for your confidence. We will be in touch with you in December to confirm everything. In the meantime, please feel free to contact one of our representatives with any question you may have.
We look forward to greeting you in your new home.
The NOCA team.